Categories: Industry

647 infrastructure projects have cost overrun of Rs 4.65 lakh crore

As many as 647 infrastructure projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.65 lakh crore, according to a report. The Ministry of Statistics and Programme Implementation monitors infrastructure projects worth Rs 150 crore and above. Of the 1,526 such projects, 647 are delayed, 393 reported cost overruns and 219 projects reported both time and cost overrun.

“Total original cost of implementation of the 1,526 projects was Rs 21,26,460.93 crore and their anticipated completion cost is likely to be Rs 25,91,823.45 crore, which reflects overall cost overruns of Rs 4,65,362.52 crore (21.88 per cent of original cost),” the ministry’s latest report for August 2022 said.

According to the report, the expenditure incurred on these projects till August 2022 is Rs 13,60,645.94 crore, which is 52.49 per cent of the anticipated cost of the projects. However, the report said the number of delayed projects decreases to 500 if the delay is calculated based on the latest schedule of completion.

Further, for 607 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Out of the 647 delayed projects, 132 have overall delays in the range of 1-12 months, 118 have been delayed for 13-24 months, 273 for 25-60 months and 124 projects have delays of 61 months and above. The average time overrun in these 647 delayed projects is 41.64 months.

Reasons for time overruns as reported by various project-implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances and lack of infrastructure support and linkages. Delay in tie-up for project financing, delay in finalisation of detailed engineering, change in scope, delay in tendering, ordering and equipment supply and law and order problems are among the other reasons. The report also cited state-wise lockdowns due to COVID-19 as a reason for the delay in the implementation of these projects.

It has also been observed that project agencies are not reporting revised cost estimates and commissioning schedules for many projects, which suggests that time/cost overrun figures are underreported, it added.

Rahul Kamat

Recent Posts

Branded Blues: How major corporations are drowning us in plastic

Plastic. It's everywhere – from the pristine peaks of Mt. Everest to the deepest trenches…

1 hour ago

Solving the structural problems with the TV audience measurement in India

TV audience measurement (TAM) aims to impartially and rigorously measure television viewership data, which is…

2 hours ago

India’s tourist hotspots set to drive job boom: 58.2 mn positions forecasted by 2033

From iconic landmarks like the Eiffel Tower and the Taj Mahal to hidden gems off…

3 hours ago

Honeywell develops innovative lightweight sensor technology for the Lilium jet

Honeywell  has been chosen by Lilium , the pioneer of the first all-electric vertical takeoff…

4 hours ago

Flexibility and cost-effectiveness: Multi-user facilities in supply chain management

In contemporary supply chain management, the paramount importance of flexibility and cost-effectiveness cannot be overstated.…

6 hours ago

How AI and automation are changing our contact center

The rapid adoption of AI and automation in the wake of the COVID-19 pandemic has…

8 hours ago